Primary School at Amager, Copenhagen


NCC Denmark is building a new primary school for the municipality of Copenhagen, using Sitecover to ensure optimum working conditions, crane capacity over the entire construction area, and reducing impact at the surroundings. (noise, dust, light)

  • Project : NCC NØAS.
  • Client: Municipality of Copenhagen
  • Contractor: NCC Denmark.
  • Size: 100 meter long and 65 meter wide, crane hook height at 24 meters.
  • Timeschedule: assembled at 25 days, to be used for 12 months, feb. 2021 to feb 2022.
  • Crane capacity: 2 cranes 12 tons hoists. total capacity bundled 22 tons.